Interest Reserve

An interest reserve is part of a loan set aside at closing to pay the loan’s own interest while a property is under construction, renovation or lease-up and does not yet produce enough income to pay it.

Formula

What is the interest reserve formula?

Interest reserve = the sum of (opening balance x periodic rate) for each period until the property can pay its own interest

Next opening balance = opening balance + interest for the period + draws funded in the period

  • Opening balance: the loan amount outstanding at the start of the period.
  • Periodic rate: the annual rate divided by the number of periods in a year (by 4 for quarters, by 12 for months).
  • Draws funded: construction or renovation advances made under the draw schedule.

Because the interest is paid from the reserve and added to the balance, the reserve also pays interest on itself. Lenders build the schedule from the draw forecast and usually round the result up. The reserve is counted in the loan commitment and in total project cost.

How was the sample bridge loan's reserve sized?

Illustrative figures. The sponsor's 96-unit renovation was financed with a bridge loan at 9.00 percent (fixed here for simplicity; most bridge loans float). The initial advance was $5,700,000, and the $1,584,000 renovation budget was funded in three draws of $528,000 at the end of quarters one, two and three. Interest is computed quarterly at 9.00% / 4 = 2.25% and paid from the reserve.

QuarterOpening balanceInterest at 2.25%
1$5,700,000$128,250
2$6,356,250$143,016
3$7,027,266$158,113
4$7,713,379$173,551
Total$602,930

Each opening balance is the prior one plus that quarter's interest plus the draw: $5,700,000 + $128,250 + $528,000 = $6,356,250, and so on. The lender set the reserve at $605,000, leaving $2,070 unused. The commitment was $5,700,000 + $1,584,000 + $605,000 = $7,889,000, and the funded balance after the reserve ran out was $7,886,930. From then on, the property's income paid interest of $59,152 a month.

How do lenders use an interest reserve?

An interest reserve keeps a loan current while the property cannot, and it can also hide trouble: a project can be late and over budget while every payment arrives on time. Credit officers read the reserve as a time budget. If construction or lease-up slips, the reserve runs out before the income arrives. Many lenders require the reserve to be rebalanced, or the borrower to deposit cash, when the schedule moves.

Typical policy treatment (illustrative): the sample bridge lender requires the reserve to cover the full projected schedule at closing, with the draw forecast as its basis. The $605,000 reserve covers the $602,930 schedule.

What are common interest reserve errors?

  • Sizing on the full commitment from day one, or on the initial advance only, instead of the draw schedule.
  • Leaving out interest on the reserve's own draws.
  • Sizing a floating-rate loan at today's index with no allowance for a rise.
  • Treating timely payments from the reserve as evidence that the project is performing.

Where does the reserve appear in the credit memo?

The reserve appears in sources and uses as a soft cost, in the loan structure section with its sizing assumptions, and in the risk section with the months of cushion it gives if completion slips. After closing, monitoring reports show the reserve balance against the remaining schedule.

Related terms

Construction draw, sources and uses, hard and soft costs, bridge loan, debt service reserve.

Where LenderBox does this work

On construction and renovation loans, LenderBox reads the budget, the schedule and the people against your credit box and keeps reading through every draw, so your team can see at each draw whether the reserve still matches the schedule.

See it worked on a deal you bring.

A 30-minute demo can run on documents you bring: LenderBox reads the file, shows the source page behind each figure, and checks the result against your credit policy.

See it on your deal
30 MINUTES. NO COMMITMENT. 90-DAY MONEY-BACK GUARANTEE.