Hard and Soft Costs

Hard costs are the costs of physical construction (labor, materials and the contractor’s work on the site), and soft costs are the other project costs, such as design, permits, fees, insurance, financing costs and the interest reserve.

Formula

What is the project cost formula?

Total project cost = acquisition or land cost + hard costs + soft costs

Hard cost share = hard costs / total project cost

Soft cost share = soft costs / total project cost

  • Acquisition or land cost: the price paid for the property or site and the closing costs of buying it.
  • Hard costs: site work, structure, building systems, finishes, unit interiors, the general contractor's fee and general conditions, and the hard cost contingency.
  • Soft costs: architecture and engineering, permits and impact fees, legal, insurance and taxes during construction, loan fees, the interest reserve, any developer fee and any soft cost contingency.

Classification varies by lender and by budget format, so the budget's own line definitions matter.

How is the sample renovation budget split?

Illustrative figures for the renovation of the 96-unit community that was later refinanced with a $9.0 million loan.

LineAmountBucket
Purchase price$7,600,000Acquisition
Acquisition closing costs$152,000Acquisition
Unit interiors (96 units x $11,000)$1,056,000Hard
Exterior and common areas$384,000Hard
Hard cost contingency (10%)$144,000Hard
Design and permits$60,000Soft
Senior and mezzanine origination fees$84,890Soft
Interest reserve$605,000Soft
Total project cost$10,085,890

Acquisition, hard and soft costs: $7,752,000 + $1,584,000 + $749,890 = $10,085,890. Hard costs are 15.7 percent of the total and soft costs 7.4 percent. The fees are 1 percent of each loan: $78,890 on the $7,889,000 senior commitment and $6,000 on the $600,000 mezzanine loan.

How do lenders use the hard and soft cost split?

Hard costs buy collateral: when they are spent, something of value is in the ground or in the units. Many soft costs do not survive a default. Fees, interest and permits have no resale value on their own. Lenders therefore look closely at how much of the loan funds soft costs, at whether the hard cost budget is supported by a contract and a third-party cost review, and at whether each bucket carries its own contingency. Draws are usually inspected against hard cost lines, while soft costs are supported by invoices.

Typical policy treatment (illustrative): the sample bridge lender requires a signed contract or a third-party cost review behind the hard cost budget and a hard cost contingency of at least 10 percent on a renovation. The sample budget carries 10 percent.

What are common hard and soft cost errors?

  • A hard cost budget built from a contractor's rough estimate with no signed contract or independent review.
  • No soft cost contingency, as in the sample budget, so a permit delay or rate rise has to come from the hard cost contingency or the sponsor.
  • A developer fee counted in cost and then treated as equity contributed.
  • Financing costs left out of the budget while the loan pays for them.

Where do budget lines appear in the credit memo?

The budget appears in sources and uses and in a project budget section, often with a column for the third-party cost reviewer's comments. The risk section addresses the contract type, the contractor's capacity and the contingency.

Related terms

Contingency, construction draw, loan to cost, sources and uses, interest reserve, environmental report.

Where LenderBox does this work

Through financial spreading, LenderBox reads the construction budget with every figure cited to the document and page it came from, so your team sees each hard and soft cost line against its source before the loan is sized.