Contingency

A contingency is a budget line set aside for costs that are expected but not yet identified, such as conditions found behind walls or price changes, so that a project can absorb surprises without running out of money.

Formula

What are the contingency formulas?

Hard cost contingency = hard cost budget before contingency x contingency percentage

Contingency used ratio = contingency spent / total contingency

  • Hard cost budget before contingency: the sum of the hard cost lines for identified work.
  • Contingency percentage: the allowance the lender and the cost reviewer accept for the project's unknowns.
  • Contingency spent: contingency released through draws to date.

The used ratio is read against percent of work complete: if contingency is being used faster than work is being completed, what remains may not cover the rest of the job. Renovations of older buildings usually carry more contingency than new construction on a fixed-price contract, because more is unknown. Many budgets also carry a separate soft cost contingency.

How was contingency used on the sample renovation?

Illustrative figures for the renovation of the 96-unit community before its $9.0 million refinance.

Hard costs before contingency, unit interiors plus exterior and common areas: $1,056,000 + $384,000 = $1,440,000. Contingency at 10 percent: $1,440,000 x 10% = $144,000. Hard cost budget: $1,584,000.

Point in the projectWork completeContingency usedContingency left
After draw 132 units$0$144,000
After draw 264 units, 66.7% of the budget$56,000 (38.9%)$88,000
After draw 396 units$144,000$0

At draw 2, 38.9 percent of contingency was used with two thirds of the work done, which looks comfortable. The final third used the remaining $88,000, so the project finished exactly on budget with nothing left. The sample budget carried no soft cost contingency; the interest reserve, set at $605,000 against a $602,930 schedule, had $2,070 of room.

How do lenders use contingency?

Contingency is the first buffer between a cost overrun and the lender's money. When it is gone, overruns fall to the sponsor, and the lender's protection depends on the sponsor's liquidity and any completion guaranty. Many lenders require a minimum contingency in the approved budget, restrict its use to approved changes, and report remaining contingency against percent complete at every draw.

Typical policy treatment (illustrative): the sample bridge lender requires at least 10 percent of hard costs on a renovation, releases contingency only for approved changes, and reports contingency remaining against percent complete at every draw.

What are common contingency mistakes?

  • Allowing contingency to be moved into general contractor profit or other lines without lender approval.
  • Reading a low contingency balance as acceptable because the project is near completion, when the last phase often holds punch-list and exterior work.
  • Treating contingency as available equity or as a source to pay interest.
  • Carrying no soft cost contingency, so delays or higher rates have no budget.

Where does contingency appear in the credit memo?

At approval, the memo states the contingency amount and percentage, what it may be used for, and how it compares with the third-party cost review. In draw and portfolio reports, it shows contingency remaining against percent complete, and any reallocation goes to the approving officer.

Related terms

Hard and soft costs, construction draw, interest reserve, loan to cost, sources and uses.

Where LenderBox does this work

On construction and renovation loans, LenderBox reads the budget, the schedule and the people against your credit box and keeps reading through every draw, so your team sees contingency used against work complete at each advance.

See it worked on a deal you bring.

A 30-minute demo can run on documents you bring: LenderBox reads the file, shows the source page behind each figure, and checks the result against your credit policy.

See it on your deal
30 MINUTES. NO COMMITMENT. 90-DAY MONEY-BACK GUARANTEE.